BNL REVIEW AGS Upgrade and Super Neutrino Beam Facility June 10 - 11, 2004 Bldg. 911B, Large Conference Room June 10, Thursday 08:30 - 09:00 Executive Session 09:00 - 09:15 Opening Remark T. Kirk 09:15 - 10:00 Overview of the Project W. T. Weng 10:00 - 10:30 1.2 GeV SCL D. Raparia 10:30 - 11:00 Cryogenic System K. C. Wu 11:00 - 11:30 AGS Power Supply I. Marneris 11:30 - 12:00 AGS RF System M. Brennan 12:00 - 13:30 Lunch 13:30 - 14:00 AGS Transition Crossing J. Wei 14:00 - 14:30 AGS Injection and Extraction N. Tsoupas 14:30 - 15:00 Beam Transport to Target D. Raparia 15:00 - 15:30 Configuration of Target/Horn and Neutrino Spectra M. Diwan 15:30 - 16:00 Mechanical Design of the Target/Horn System S. Bellavia 16:00 - 16:45 Target Hill and Service Building A. Pendzick 16:45 - 17:15 Conventional Facilities and Utilities T. Nehring June 11 Friday 08:30 - 09:00 Executive Session 09:00 - 09:30 Horn Power Supply A. Zhang 09:30 - 10:00 Radiation Shielding D. Beavis 10:00 - 10:30 Near Detector S. Kahn 10:30 - 11:00 ESSH E. Lessard 11:00 - 11:30 Cost Estimate K. Mirabella 11:30 - 12:00 Construction Schedule and Operational Scenarios W. T. Weng 12:00 - 13:30 Lunch 13:30 - 14:30 Questions and Answers 14:30 - 15:30 Executive Session 15:30 - 16:15 Closeout Things to do for review, white paper 1) write beam section Hkirk, Skahn, MVD 2) new target geometry Skahn, MVD 3) examine horn focusing geometry in more detail, completely redesign horn to take advantage of new manufacturing technologies. JGallardo 4) examine errors on the spectrum due to errors in production SKAHN 5) Examine 1 deg offaxis running in more detail. MVD 6) loss of flux due to various practical issues: shielding around horn, windows for He, window for tunnel (if evacuated). Window for tunnel if He, water in the horns... 7) Near detector. How to use ? Skahn 8) Can near detector be farther ? Skahn Things to do for APS study from us 1) write paper including antineutrino running. 2) Examine 1290 km 3) Examine effect on CP measurement due to ambiguities from th23 and Delta m21. Longer term: 1) Water Cherenkov simulation 2) Detector optimization for containment 3) Detector optimization for electron ID 4) Photo multiplier R&D 5) Liquid argon versus water cherenkov. 9) More long term: simulate AlBeMet geometry with target integrated into horn, plasma lense (?)