1.  RUN summary
 
Kblive ~ 1.8 x 10^12   ~ 2/3  1998 data
SMX tapes  543 (2002)  108 (2001)

2.  What acceptance do we expect?

                                              PNN1                                 PNN2

      bottom line                 0.5 x Acc_98                    0.5 x Acc_96

                                                                   ~ Sen_98

                                                      Room for improvement!

3. What background level do we expect?

     *     Kinematic background     (no estimate!)
     **   Beam background    ( may increase by 10!)

4. Analysis plans

    1) Locations

           PNN1                             PNN2                          1GAMMA
        TRIUMF                        BNL                             JAPAN, INR

    2) PASS0 for raw monitor data
         -- coding, debugging and calibrations

    3) PASS1 for raw SMX data
         --maintaining acceptance, reducing data volume

    4) PASS2 for full reconstruction
         --background analyses

5. Areas requiring significant work

     1) Beam instrumentaion (Peter, Jingliang...)
           a) Codes for new systems (almost done)
           b) Pile-up protections (under way)
           c) Double pulse fit (under way)
           d) Timings (almost done.)
           e) Energy (almost done.)
           f) B4 position (almost done.)
      2) Target (Jim, Bipul, Benji ...)
           a)  SWATH --> SWATHCCD (under way)
           b) ADC/TDC calibration (done ?)
           c)  Target aligment (under way)
     3) UTC (Shaomin, Toshio, Joel, George, Kentarou  ...)
           a) Codes for high rate (mostly done.)
           b) B-filed correction (almost done.)
           c) UTC aligment (under way)
           d) Inner foil layer efficiency loss (under way)
      4) Range Stack enegy (Benji, Jim...)
           a) "1-st order" RS-ADC calibration (almost done)
           b) "2nd order" RSMON-based RS energy calibrations (under way)
      5) RSTDC (Dima, David...)
           a) RS TDC timing calibration (almost done)
           b) TRKTIM (done?)
           c) EV5 (done?)
           d) ELVETO (done?)
           e) TRKRNG (not yet)
           f) Case for TDC  time missing (under investigation)
      6) TD fitting (David, Tetsuro ...)
           a) Pulse shape and flag calibration (almost done)
           b) Recover accidental loss in TD fit (under investigation)
      7) Photo veto  (Joe, Takeshi, Tesuro)
           a) BV/EC/CM (working but need fine tunning)
           b) BVL/CO/DPV coding (under way)
           c) Rejection (under investigation)
      8) RSSC (Shaomin)
           a) Coding for new RSSC (almost done)
           b) Calibration (basically done)
           c) Efficiency loss (under investigation)
      9) Data quality and scalers (Steve...)
           a) Glitch log/bad_run list (under way)
           b) Scalers (under way)
     10) Data processing machinery (Joe, Shaomin, Jingliang ...)
           a) Pass0 streaming (under way )
           b) Pass1 (under investigation)
           c) Pass2 (under way)
           d) Ntuple skimming (not yet)
     11) UMC (Takeshi, David...)
           a) BV-Liner for E949 (done)
           b) Beam profile (under way)
           c) UMC in linux (?)
           e) Codes modfications and simulation for some new subdetectors and beam counters (mostly done)

Conclusions

Most codes, scripts  and calibration work are done. Modification and codes for the new subdetectors
are still under way. We expect background study can be conducted within a couple of months.