Summary PHYSGI Meeting 7/25/94
B. Gibbard
Next Meeting:
The next meeting will be Monday, August 1, 11:30 - 12:00, in Rm 2-160.
Production User Input for PHYSGI01:
- E881 & E850 were represented at this week's meeting.
- During the past week the major CPU intensive user was E881
(Hackenburg et al). Production CPU usage by other users has been small and
intermittent. There continues to be substantial tape copying activity on
PHYSGI01.
- E850 expects to begin production processing on PHYSGI03 this week, see
"Other Issues", Item 4, below.
- E881 expects to continue its use of PHYSGI01 and may extend its usage to
PHYSGI03. It was estimated that E881 is approximately 3/4 done with its
data analysis pass.
All experiments which anticipate running more than an single occasional
production job during a given week should attend the
scheduling meeting. If that is not possible they should notify Bruce
Gibbard (gibbard@bnl.gov) and Tom Throwe (throwe@rsgi02.rhic.gov)
of their needs by Email prior to the Monday 11:30 meeting.
Plan for week beginning 7/18/94:
The currently established rules will remain in effect for the
following week. These rules are intended to give a modest
advantage to experiments involved in the current AGS run.
- A production process is defined as a process which would accrue an hour or
more of CPU time in 8 hours of uncontended running.
- Each experiment is currently allowed to run up to 6 concurrent "production"
process per computer, only one of which may be run at full priority, (100).
- Experiments not actively engaged in the current AGS run must nice all
additional "production" process to 4 (104).
- Experiments which are actively engaged in the current AGS run may nice one
additional "production" process to 2 (102) but are required to nice
"production" processes beyond the first two to 4 (104).
- Extended use of a tape drive is defined as use which extends for more
than 1 hour.
- In the presences of demand by other experiments for tape drives, no
experiment should make extended use of more than 2 tape drives.
- Experiments not actively engaged in the current run should limit their
extend use, in the presence of demand by other experiments, to 1 tape
drive.
Other issues:
- There have been numerous reports of network problems associated with the
use of PHYSGI01 as well as other Physics Department machines resently. CCD
believes that Charybdis, the router serving Physics, is heavily overloaded.
Parts are on order to upgrade it and it is hoped that this near future upgrade
will substantially relieve these recently observed problems.
-
The interaction of private multi-cast tunnels with MBone tunnels has the
potential for substantially increasing network traffic. In the absence of
an important need for such tunnels, their use is discouraged on subnets in
the Physics Department.
-
At this time there are no known problems with the 8mm tape stackers.
-
The new challenge machine intended to replace PHYSGI01 is now in operation
as PHYSGI03. Its function will remain that of a simple Ethernet connected
compute server until the end of the AGS run. Some time not long after the
end of the run it will be equipped with the PHYSGI01 peripherals and will
replace PHYSGI01. It currently mounts the PHYSGI01 file system and all of
the PHYSGI01 accounts are valid on it. Groups who want to have it mount
private file systems which are currently mounted by PHYSGI01 should change
export permissions appropriately and notify Tom Nepsee by Email of this
desire.
Users of PHYSGI01 are still strongly encourage to set a
mail forward
from their working account on PHYSGI01 to an account on a machine where
they frequently check their mail so that they can be easily contacted.