Minutes of November 12, 1996 E821 Schedule Meeting Wuzheng Meng presented the inflector plan. The Cryo techs will need about two weeks to hookup the inflector to the cryo system. John Benante said the inflector should be in a state where they can start the hookup around Nov.18. Therefore, we should be ready to cool-down the inflector around Dec.4. Ralf Prigl discussed the magnetic field shimming progress. They made extensive magnetic measurements over the weekend. They have now accomplished the shimming program needed so we can run in 1997! Congratulations to the shimming team on this great success! They will do more measurements and shimming with iron in parallel with higher priority activities, ie. the inflector test, etc. They plan to install the Surface Correction Coils starting around Dec.2. It will take about two weeks. Joe Scaduto will come up with a plan to remove the turn-table. He will call a meeting to review the plan. Hopefully, we can remove the turn-table and install the floor and stairs before the inflector test begins. Mike Mapes discussed the vacuum system. They are turning out two chambers per week. We have one done now in Bldg. 919. Lou Snydstrup said he should be ready to start installing the vacuum chambers around Dec.9. We will have to interface carefully with the SCC installation and the inflector test. The quad team wants to test one quad with full-field before we warm-up for cryostat vacuum maintenance. The project schedule is shown below. Respectfully submitted - Bill Morse. 96 97 OctNov Dec Jan Feb Mar Task Name 28 12 25 9 30 13 27 10 3 17 Shim Magnetic Field wit XXXX---------------------------- Install SCC | .XXXX . . . . . . Substation | . . XXX. . . . . Prototype Kicker Tests XXXXXXXXXXXX . . . . . . Install Vacuum Chambers | . XXXXXXXXXXX. . . . Install Detectors | . . XXXXXXXXXXXXXXXXXXXXX Remove turn-table | XX . . . . . . . Install floor and stair | . XXX . . . . . . Install Quad Pulsers | . . XXXXXXX--------------- Beamtube Trolley Instal | . . . XXXXXXX. . . Monitor and Plunging Pr | . . . XXXXXXX. . . Install Infl in Chamber | . . . . . . . . Install Infl in 919 XXXXXXXXX. . . . . . . Inflector Test in Ring | . XXXX . . . . . . Cryostat Vacuum Mainten | . . XXXXXXXXXXX---------- Vacuum System Test | . . . . XXXXXX . . System Tests | . . . . . XXXXX----- AGS FY97 Run | . . . . . . M . Tune beam and inflector | . . . . . . XXXX-