Dear detector group, Here's a first go at a schedule for getting things set up for the flash test. There are a few question marks; please look this over and comment. Any omissions, corrections or additional information? We need to have everything operational for 4 detector stations by May 15. Thanks! Jim Detector Schedule for Spring Flash Test I. Detectors 1 detector on floor (perhaps located just outside ring) May 1 3 other detectors ready to be installed in ring May 1 All four detectors with FSDs May 1 (New FSD tubes delayed due to Hamamatsu mistake) with PSDs May 7? 1 boron detector, new tubes 1 boron detector, old tubes 1 old style detector, new tubes 1 old style detector, old tubes II. VME and custom Electronics, installed, cabled WFDs and MTDCs for 4 detector stations. May 1 Flight simulator set up to excercise electronics May 1 electronically and also through LEDs Derandomizers May 7 (?) (They are being assembled now) 15 volt power for bases May 1? (The parts are ordered, should be no delay) PSD electronics(VME) May 1 PSD electronics- floor May 7 (?) III. CAMAC electronics CAMAC to VME controllers May 7 Lecroy Discriminators May 1 Scalers don't have Programmable GG May 1 IV. Wire in NIM electronics Gating signals: May 7 Start, stop, markers for WFDs and MTDCs Gating for bases Early signal from MCR indicating spill Gating for Laser and LEDs Gating for flight simulator Gating for FB ADCs Start/stop for TDCs V. Calibration Laser May 1 LED driver May 1 (delivery schedule not known, but we have two units) FB crate, controller, ADCs, TDCs May 7 VI. Begin testing four complete stations May 7 VII. Lost muon detector ? VIII. Readout for beam monitors ? IX. Wire chambers ? X. LORAN-stabilized 10 MHz May 7? Clock fanouts May 7? (currently being tested) Need: Cables + manpower!