***************************************************************** * * * Main Plan * * * ***************************************************************** 1) Get the trigger/DAQ ready (several days --- George) 2) Check for catasrophic failures (~1 day --- shift) 3) Verify UTC functionality after bubbler replacement! (Toshio/shift) 4) Finish the replacement/verification of new filters for the RSMON system on the T-counters (several days --- Jim/Neil/Henry/shift). 5) test the new MT2A board, couple of days? (George) 6) measure RS light yield (after 2 years --- Ilektra) 7) ----------------------------------------------------------------- - Speculative ideas - ----------------------------------------------------------------- 1) Can we learn anything about z-dependence of T*2 inefficiency? 2) Can we learn what is wrong in the CEX trigger? (probably not) 3) deploy TD's on VC? ----------------------------------------------------------------- - Post Run Plans - ----------------------------------------------------------------- 1) reinstall the us EC for protection of the EC and detector (this should only be done after the T-counter filter replacement) after the cosmic shifts are over ~1 week.